"When will my driveway be finished?" is the most common question we get after a client signs off on a quote. The honest answer: it depends on the size, material, site conditions, and โ let's be real โ Melbourne's unpredictable weather.
Here's a realistic day-by-day timeline for a typical brick paving driveway project (40โ50mยฒ) in Melbourne's south-east, along with factors that can speed it up or slow it down.
The timeline starts before the first excavator arrives. Good contractors handle these steps in advance:
This is the noisy bit. The crew arrives early (7am typically) and:
Time: 1 day for 40โ50mยฒ. Add half a day if there are complex edges, retaining walls, or large trees near the work area.
The most critical phase of any paving project. A bad base means sinking, shifting pavers within a few years.
Time: 1 full day. Base preparation is slower if ground conditions are poor (soft soil, clay, water issues).
The exciting part โ pavers go down. A skilled crew of 2โ3 can lay 40โ50mยฒ of standard brick pavers in a day.
Time: 1โ2 days depending on pattern complexity and cutting requirements. Simple rectangular driveway with stretcher bond: 1 day. Herringbone with curved edges and multiple cuts: 2 days.
Time: Half to full day.
Foot traffic: Immediately after final compaction. You can walk on the paving the same day.
Vehicle traffic (standard paving): Wait 24โ48 hours after final sanding to drive on it. The sand needs to settle fully.
Vehicle traffic (permeable paving with aggregate joints): Drive on it immediately โ aggregate joints don't need settling time.
Sealing: If you're sealing natural stone or concrete pavers, wait 4โ6 weeks after installation. This allows the sand to settle and any efflorescence to wash away naturally.
Brick paving driveway (40โ50mยฒ): 4โ6 working days from demolition to completion.
Concrete driveway (40โ50mยฒ): 2โ3 days for pour and finish, then 7 days curing before you can drive on it.
Small patio or path (10โ20mยฒ): 2โ3 days total.
Large driveway + patio (80โ100mยฒ): 7โ12 working days.
Read our paving cost guide for Melbourne for pricing breakdowns by material and size, and our guide to choosing the right paving for your specific project.
For brick paving, wait 24โ48 hours after final sanding and compaction. For concrete, wait at least 7 days. For permeable paving with aggregate joints, it's fine immediately.
Yes โ especially in Melbourne. Excavation, base compaction, and sanding all require dry conditions. A light drizzle won't stop laying pavers, but heavy rain or persistent wet weather pushes the schedule out significantly.
A small patio (15โ20mยฒ) typically takes 2โ3 working days. A larger entertaining area (40โ60mยฒ) takes 4โ6 days.
Reputable contractors build weather buffers and scheduling flexibility into their timeline. When we quote 10โ14 calendar days for a 5-day project, it accounts for Melbourne rain, material deliveries, and curing time โ we'd rather under-promise and over-deliver.
Not necessarily, but we recommend being available on Day 1 to confirm site access, parking, and any specific requirements. A key contact by phone is sufficient after that.
Free written quotes across Melbourne's south-east. We'll give you a realistic timeline before you commit.